I & II. Status
of Miami River Federal Navigable Channel Maintenance Dredging Project
& Funding and Status of “Bank to Bank” Maintenance Dredging
Project & Funding –
Mr. Jerry Scarborough, Army Corps of Engineers (ACOE), stated that $3
million of the $27.8 million previously appropriated by Congress for the
Miami River maintenance dredging project has been reprogrammed for
acceptance section 3 of 15. Mr. Scarborough noted approximately $9.5
million in reprogramming is still needed to continue dredging through
acceptance sections 4-6, before the September 30 end of Fiscal Year
2005, without a temporary demobilization.
Mr. Scarborough stated he would continue working with the
ACOE’s South Atlantic Division and Headquarters to secure
reprogramming of the federal cost share in order to avoid temporary
demobilization of the project. Mr. Brett Bibeau, MRC Managing Director,
thanked the ACOE for their continued effort and support for the
Miami River
maintenance dredging project.
Mr. Jeff McWilliams, Bean Environmental, stated he expected the dredging
of acceptance section 3 to be completed by
July 25, 2005
. Mr. McWilliams asked if
funding necessary to award dredging within additional acceptance
sections would become available before completion of acceptance section
3. Mr. David Cole,
Weston/Bean, stated the ACOE’s just in time funding impedes the
dredgers and sediment processing plant from working efficiently and
suggested the ACOE award multiple consecutive acceptance sections. Mr.
Scarborough acknowledged Mr. Cole’s concerns.
Mr. Carlos
Espinosa, Miami-Dade County Department of Environmental Resource
Management (DERM), suggested the ACOE send DERM letters requesting the
local cost share for acceptance sections 4-6, in order to have the
payment processed. Mr.
Scarborough replied the ACOE would send the County a request for the
local cost share on acceptance sections 4-6.
Mr. Espinosa stated the ACOE provided the County with the
requested paperwork required to establish an escrow account for the
local cost share, and it was currently under review by the
County
Attorney
’s Office.
Mr. Ancil Taylor, Bean Environmental, asked if the funding is not in
place to award acceptance section 4 prior to the July 25 completion of
acceptance section 3, would the project be forced into a temporary
demobilization. Mr.
Scarborough noted the ACOE was trying to avoid a temporary
demobilization, and noted any such temporary demobilization and
remobilization would be added project costs for all cost shares.
Mr. Taylor and Mr. Scarborough discussed “dredging the tow”,
and the approval of acceptance sections 1-3.
Mr. Cole noted the ACOE is yet to respond to a few formal
requests for information from the contractors.
Mr. Scarborough stated Mr. Cole should expect to receive the
ACOE’s response to the contractor’s request, regarding dredging near
unconsolidated bulkheads, before the end of the day.
Mr. Espinosa indicated that all components of the local cost share are
currently available through acceptance section 9, therefore only the
federal cost share is necessary to continue dredging.
Mr. Evan Skornick, South Florida Water Management District (SFWMD),
stated the District is working on the 2nd round of grants
from the Florida Inland Navigation District (FIND), a $1.5 million cost
share for acceptance sections 9-11.
This brings the approved and appropriated FIND cost share total
up to $3.8 million of the pledged $6 million.
III.
Update
River
Utility Crossings –Mr. Bibeau stated it was his understanding that all future
utility relocations seem to be on schedule for removal prior to the
arrival of the dredger. As noted by Mr. Rene Perez, ACOE, during the
June 15, 2005
Dredging Subcommittee meeting, a series of cables and utility lines at
NW 22nd Avenue
, within AS 6, are expected to be replaced and relocated by
August 5, 2005
. Mr. Scarborough concurred,
noting the ACOE does not foresee any problems with utility crossings at
least through acceptance section 6.
IV.
Status of Removal of NW 5th Street Bridge Prior to Dredging
within that Acceptable Section
– Mr.
Bibeau reported the NW 5th ST Bridge had recently been struck
by a vessel under tow, and will remain in the “locked up” position
until the Florida Department of Transportation (FDOT) analyzes its
options and determines a feasible solution. Mr. Bibeau stated the Army
Corps of Engineers declared the NW 5 ST bridge as a hazard to navigation
in 1929, due to several deficiencies which were constructed inconsistent
with the permitted bridge design, and the bridge has been struck by
vessels under tow approximately 13 times in the past decade.
In addition, every time the bridge is struck, the lengthy repairs
are conducted with the bascule leafs in the open position, blocking
vehicular and pedestrian traffic. Mr.
Bibeau stated the FDOT has completed the PD& E for the funded
replacement of the NW 5 ST Bridge, and after obtaining 30% completion of
construction documents, could technically issue an RFP to create a new
bridge. Mr. Bibeau added FDOT is also considering repairing the bridge,
if an expedited construction of a new bridge does not prove a viable
option. Mr. Bibeau suggested that FDOT examine the possibility of
replacing the NW 5 ST Bridge before commencing the planned replacement
of the
NW 12th Ave.
Bridge, which is not deemed a hazard to navigation.
The dredging subcommittee noted the currently broken NW 5 ST
Bridge is constructed well into the federal navigable channel; therefore
the dredgers would be forced to proceed around the structure, leaving
significant quantities of sediments behind.
Mr. Scarborough stated the ACOE would contact the USCG about the
issue.
V.
New Business - The
Dredging Subcommittee confirmed the next regularly scheduled third
Wednesday of the month meeting for August 17, 2005, 10 am, Robert King
High, 1407 NW 7 Street.
The meeting
adjourned.
|