For more information, contact us via email at
miamiriver@bellsouth.net

MIAMI RIVER COMMISSION 
c/o Robert King High
1407 NW 7 St.,  Suite D
Miami, FL 33125  
  Phone 305-644-0544
Fax 305-642-1136

 

 

 

 

This site
prepared and designed by
Mark Sell Communications, Inc. Public Relations

  MIAMI RIVER COMMISSION
   DREDGING COMMITTEE MINUTES:
  Minutes of meeting
Aug. 16, 2006
10:00 AM
(THIS IS A PUBLIC DOCUMENT)
The Miami River Commission’s (MRC) Dredging Working Group met as regularly scheduled on the third Wednesday of the month, August 16, 2006, 10 AM, at 1407 NW 7 ST.  Mr. Eric Buermann chaired the meeting, and the attendance list is enclosed. 

I & II. Status of Miami River Federal Navigable Channel Maintenance Dredging Project & Funding and Status of “Bank to Bank” Maintenance Dredging Project & Funding – Mr. Brodie Rich, United States Coast Guard (USCG) Bridge Branch, asked MRC staff to make the following revisions to the Dredging Working Groups July 19, 2006 meeting minutes: Page 4, Bullet 4: The NW 5th Street Bridge will feature a 128-foot clear and unobstructed horizontal clearance w/o fenders, 110-feet unobstructed horizontal clearance between the fenders, and 150-foot horizontal clearance with spillways for water conveyance; Mr. Rich added that the Army Corps of Engineers (ACOE), rather than the Coast Guard Sector Miami, may require the USCG Bridge Branch to require FDOT to remove their land in the federal navigable channel as a portion of the USCG’s Bridge demolition and/or construction permits.  MRC staff agreed to incorporate the aforementioned changes, and the Dredging Working Group approved the revised July 19 meeting minutes.

Mr. Rene Perez, Army Corps of Engineers (ACOE) Project Manager for the Miami River Maintenance Dredging Project, stated the ACOE remains planning to award acceptance section (AS) 7 of 15 in late September 2006, using the $3.5 million Fiscal Year (FY) ’06 federal appropriation.  Mr. Perez noted the contract provides 60 days to remobilize from the award of the next acceptance section (late September to late November), and recommence dredging in late November 2006, following the hurricane season as requested by their contractors.  Mr. Perez noted the currently available FY ’06 federal cost share is only sufficient to complete dredging within AS 7, and federal FY ’07 commences October 1, 2006 , when an additional $3.5 - $7 million may be appropriated by Congress for the project, which is sufficient to dredge AS 8 of 15.  Mr. Perez noted the contractors estimate completion of one AS per month, therefore under this scenario, the project would incur its second of five allowable temporary demobilizations in January 2006, until any additional federal cost share is potentially appropriated by Congress in FY ’08, which commences on October 1, 2007.  Mr. Perez reported their contractor, (Weston Solutions and Bean Environmental joint venture), recently requested the ACOE further postpone awarding AS 7 until late March 2007, resulting in recommencing dredging by late May 2007, in order to potentially capture FY ’06, FY ’07, and FY ‘08 federal appropriations to avoid an additional temporary demobilization & remobilization by possibly avoiding any potential future funding gaps.  Mr. Perez noted the ACOE dredging contract officer was checking regulations which may impact the contractors request to delay awarding AS 7 until late March 2006, and hadn’t made any decisions yet regarding the request.  Mr. Perez stated the ACOE capability figure for the FY ’08 budget is $26 million, and noted the dredging contract expires in April 2009, therefore FY ’07 ($3.5 - $7 million) and FY ’08 are the last two opportunities to secure the $26 million federal cost share balance due to complete the project under the current contract. 

Mr. Brett Bibeau, MRC Managing Director, noted the Senate Energy and Water Bill’s $7 million line item for Miami River maintenance dredging is a single year record high for the project, and thanked the Honorable Senators Nelson and Martinez for their continued support.  In addition, Mr. Bibeau thanked the City of Miami and Miami-Dade County for including their respective cost share balances due to complete the project in their draft FY ’07 budgets, which will be considered by the City and County Commissions in September 2006.  Ms. Lucy Perez, South Florida Water Management District (SFWMD), reported the Florida Inland Navigation District (FIND), ranked the SFWMD’s Miami River maintenance dredging grant application as the top priority, resulting in FIND awarding a $2.16 million grant, completing their pledged cost share balance due to finish the project.  The Dredging subcommittee noted the final portions of the 31% local cost share to complete the $80 million dollar Miami River maintenance dredging project remains on track to be fully appropriated and available no later than September 30, 2006.

Mr. Carlos Espinosa, Director of the Miami-Dade County Department of Environmental Resource Management (DERM), asked Mr. Perez whether the potential postponement of awarding AS 7 after FY ’06 ends on September 30, 2006 , would impact the currently available $3.5 million FY ’06 congressional appropriation for the project.  Mr. Perez replied if the currently available FY ’06 funding for the project is not obligated by awarding AS 7 before the September 30 end of FY ’06, the funding may be subject to reprogramming to other ACOE projects immaterial of the new rules, because the Miami River dredging project is considered “operations and maintenance” versus projects where public safety is at risk and lives at stake.

Mr. Espinosa asked if the ACOE encumbered the FY ’06 appropriation via awarding AS 7 just before the September 30, 2006 end of FY ’06, could they consider extending the 60 day timeline for remobilization, because it is logical to postpone dredging in order to tie in potential FY ’08 funding, in order to avoid additional demobilization / remobilizations.  Mr. Perez noted since FY ’06 and FY ’07 federal appropriations would only be sufficient for two months of dredging (AS 7-8), even if the contractors request to postpone recommencing dredging to June 1, 2006, the funding would be used by August 1, 2006 triggering the second allowable temporary demobilization, several months before the potential FY ’08 federal appropriation for the project may become available.  Mr. Perez added the $4.5 million federal appropriation for the additional volume caused by Hurricane’s Katrina, Wilma, Rita ands Ophelia will be expended throughout the remaining acceptance sections, and can’t be used all at once.  Mr. Bibeau asked Mr. Perez how much of the $4.5 million hurricane “supplemental” funding was used to remove the sunken vessels shown in the pictures Mr. Perez provided during the Dredging subcommittee’s July meeting, and Mr. Perez replied $100,000.  

On behalf of Weston Solutions, Mr. Mark Taylor noted the dredging contractors would like to remobilize in order to complete as much of the remaining dredging project as possible, without incurring additional temporary demobilizations and remobilizations. 

Mr. Taylor noted the contractors therefore requested postponing awarding AS 7 until late March 2007, in order to recommence dredging no earlier than June 1, 2007 .

Mr. Buermann asked Mr. Espinosa to provide a funding update of the project on behalf of Miami-Dade County , and Mr. Espinosa noted the County’s Budget Office is continuing to explore providing local advanced funding, as well as investigate a variety of funding options, including seeking cost shares from the State of Florida , City of Miami , and FIND, for the local project sponsor to potentially provide a $26 million loan for the federal cost share balance due to complete the project without additional temporary demobilizations and remobilizations.  Mr. Espinosa noted all cost shares of the local project sponsor’s potential loan of the federal cost share balance due would be repaid, subject to future congressional appropriations.  Mr. Espinosa stated the County may seek a $13 million cost share of the grand total $26 million loan from the State of Florida in FY ’07 (July 1, 2006 - June 31, 2007), in addition to the $800,000 difference between the County’s FY ’06 $4 million request and the State’s $3.2 million FY ’06 appropriation.  Mr. Espinosa noted he had spoken to the new Miami City Manager Pete Hernandez about participating in the potential local advanced funding, whom seemed amenable to the possibility.  Mr. Espinosa stated the County would begin conducting high level meetings with representatives of the additional local cost share partners to discuss local advanced funding.  Mr. Espinosa added he had worked with the ACOE to determine the estimated federal cost share balance due to complete the project is $26 million.  Mr. Bibeau explained the $26 million takes into account the lowest possible level of FY ’07 funding, $3.5 million, yet if the FY ’07 Senate Energy and Water Bill’s $7 million line item is approved in conference, the estimated Federal cost share balance due to complete the project becomes $22.5 million. The Dredging subcommittee noted if the local advanced funding is made available by October 1, 2006; the project would avoid any additional temporary demobilization / remobilizations, and considering the estimated dredging rate of one acceptance section per month, the remaining acceptance sections (AS 7-15) would be completed by August 2007.  The Dredging subcommittee further noted the project’s benefits will not be realized until dredging is completed to the mouth of the federal navigable channel.  Mr. Buermann noted FY ’08 is the last fiscal year before the ACOE’s 5-year dredging contract expires, issuing a new contract would require Congressional authorization, and any new contract would probably include a significant increase to the price per cubic yard removed, set in the current 2004 contract.  Mr. Espinosa stated everyone wants to complete the widely supported project, and the $40 million spent thus far would be wasted if the project isn’t completed.  Mr. Bibeau added the ACOE requested local private and public utility lines crossing the Miami River be relocated to deeper depths beneath the federal navigable channel, in anticipation of dredging, and relocating the utilities has cost approximately $55 million thus far, which would have been unnecessary if the dredging project is not completed.

Mr. Bibeau provided the revised PowerPoint presentation to Mr. Espinosa and Ms. Misty Brown, Miami-Dade County Intergovernmental Affairs, regarding the project’s status, which incorporated the recommended revisions discussed at previous Dredging subcommittee meetings.  Mr. Bibeau reported per the dredging subcommittee direction, the PowerPoint presentation was used in recent individual briefings with the following Honorable County Commissioners:  Vice-Chair Dennis Moss, Katy Sorenson, Jose “Pepe” Diaz, and staffs of Commissioners Sallye Heyman, Carlos Gimenez, and Rebecca Seijas.  Mr. Bibeau noted Mr. Jose Fuentes, SFWMD, attended the briefings with Commissioners Sorenson and Diaz.  Mr. Bibeau added the MRC scheduled a meeting with Commissioner Barbara Jordan in September, and is attempting to schedule briefings with the remaining County Commissioners .

Mr. Bibeau stated similar to the successful FY ’07 approach, the MRC recommended project stakeholders write ACOE General Strock and Mr. Rob Portman, Director of the President’s Office of Management and Budget (OMB), in support of including the $26 million federal cost share balance due to complete the project in their FY ’08 budget submittal to Congress, which would increase the probability for Congress to appropriate the amount.  Mr. Bibeau noted the ACOE is currently creating their FY ’08 budget recommendations, which will be submitted to OMB early this fall.  Mr. Bibeau thanked everyone whom has already written the recommended support letters, and distributed copies of the letters including but not limited to: City and County Commissioners , Greater Miami Chamber of Commerce (GMCC), South Florida Water Management District (SFWMD), marine industrial businesses, Marine Industries Association of South Florida, Marine Council, Miami River Marine Group, and Miami River developers.

Mr. Bibeau reported the MRC Executive Committee authorized his trip to Washington DC on September 6-7, joining the GMCC advocacy group in support of obtaining the federal cost share balance due to complete the project.  Mr. Bibeau added he planned to meet with representatives from the ACOE and OMB during the September 6-7 trip to the Capital, in support of including the estimated $26 million federal cost share balance due in the Administration’s FY ’08 budget submittal.  Mr. Bibeau thanked Mr. Matt Leopold, Governor Bush’s Office of Federal Intergovernmental Affairs, whom agreed to attend the meetings to express the Governor’s continued support for the President to include the $26 million Federal cost share balance due to complete the project in the FY ’08 budget submittal.  In addition, Bibeau plans to meet with staff from the House and Senate Energy and Water Committees, and Honorable Senators Nelson and Martinez , in support of obtaining their single year record high $7 million congressional appropriation for the project during the FY ’07 conference.  Mr. Bibeau thanked the representatives of Miami-Dade County, the Greater Miami Chamber of Commerce, and the MRC’s Federal Intergovernmental Affairs consultant, Phil Bangert, Patton Boggs, whom will participate in the upcoming DC meetings as well.

Mr. Bibeau asked Mr. Espinosa for an update regarding the County Attorney ’s review of the local advanced funding Memorandum of Agreement (MOA), which the ACOE originally provided the County for consideration prior to the project’s first allowable temporary demobilization.  Mr. Bibeau noted the local advanced funding MOA guarantees the federal cost share component of the provided local advanced funding will be repaid, subject to continued future congressional appropriations.  Mr. Bibeau reported Congress has made multi-million dollar appropriations for the project for the past 8 consecutive fiscal years, adding up to over $31 million thus far.  Mr. Espinosa stated the County would further consider moving forward with the potential local advanced funding MOA in September 2006, after the Board of County Commissioners August recess.  Mr. Perez noted that if the Board of County Commissioners approves the MOA, it would be transmitted to the ACOE for execution, before they would be able to accept the funds to award dredging in future acceptance sections.

III. & IV. Update River Utility Crossings & Status of Removal of NW 5th Street Bridge Prior to Dredging within that Acceptable Section - Ms. Pat Hanson, ACOE, stated the ACOE continues to keep all private utility companies and property owners on schedule in regards to water lines/utility crossings.  Mr. Buermann asked if the rate at which the lines are relocated is sufficient to allow the contractors to dredge without delays, and Ms. Hanson replied yes, the utility relocation schedule is based on the fastest potential timeline to complete the dredging project, without factoring in any additional temporary demobilization and remobilizations.

Mr. Rich asked when the dredgers would arrive at the NW 5th Street Bridge, and Mr. Bibeau replied NW 5th Street Bridge is located in AS 11, therefore the earliest case scenario would be recommence dredging in late November 2006, at the estimated rate of completing one acceptance section per month they would arrive in AS 11 is April 2007.  Ms. Hanson asked Mr. Jose Barrera, Florida Department of Transportation, if the NW 5 ST Bridge replacement project was fully funded, and Mr. Barrera replied yes, there was a tight yet sufficient available budget to complete the NW 5 ST Bridge project.  Mr. Barrera added the removal of the existing NW 5 ST Bridge is scheduled for March 2007; therefore it would be removed before the earliest possible date the Miami River Dredging contractors would arrive in that vicinity.  The MRC dredging subcommittee thanked the FDOT.

Ms. Hanson explained that the ACOE is unwilling to expend funds to dredge the FDOT owned land and rock adjacent and beneath the NW 5th Street Bridge, because in part the volume is not included in the original contract.  Ms. Hanson stated the ACOE will require the FDOT to remove their land improperly located in the federal navigable, as a component of the ACOE’s permits required for the FDOT’s replacement of the NW 5 ST Bridge.  Ms. Hanson noted the opportunity for the FDOT to contract separately with the ACOE’s dredging contractors, which may lead to FDOT cost savings because they would avoid the mobilization and demobilization costs.

V. New Business - Mr. Bibeau distributed copies of the dredging project’s completed GMCC 2006-2007 Federal Legislative Proposal/Issue forms, which the MRC submits annually in support of the local project sponsors Federal cost share appropriation requests.  Mr. Bibeau thanked the GMCC for maintaining their “Priority” support for completing the long awaited Miami River maintenance dredging project.  

The Dredging subcommittee confirmed the next regularly scheduled third Wednesday of the month meeting for September 20, 2006, 10 am, 1407 NW 7 ST.

The meeting adjourned.

  HOME        CALENDARS       ABOUT THE RIVER          ABOUT THE COMMISSION         DREDGING      GREENWAYS   
URBAN INFILL PLANS          
STORMWATER RETROFITTING            MINUTES OF MEETINGS      LINKS