Introduction
The US Army
Corps of Engineers (USACE) is in the process of preparing plans and
specifications for the Miami River Maintenance Dredging project.
The USACE will issue a Request for Proposals rather than a
Solicitation of Bids. This
means that the contractors will not only provide a price for the work
but they will propose the method of dredging along with the proper
handling and disposal of the dredged material.
The USACE will select the dredging contractor based upon
“best value to the government” which may not be the lowest
price. Best value
considers the dredging and disposal methodology, the environmental
impacts, community impacts, etc., in addition to the cost.
Therefore, the dredge type will be determined during the
selection process. The
work is expected to be completed by mechanical dredging.
Disposal
Based upon
extensive testing by federal, state, and local environmental agencies,
the material to be dredged is considered contaminated but it is not
hazardous. The disposal
or reuse of the dredged material will be required to meet applicable
environmental standards.
Dredging
A
dredge removes material from within the channel width, as shown in
Figure 1. The channel
width is also the dredging limit.
As the dredge removes the material from the channel width,
material adjacent to the channel will fall into the hole created as
the dredge removes material. The
dredge will continue to remove material from the channel width until
material ceases to fall into the channel.
This creates the channel slope.
The steepness of the channel slope depends upon the type of
material. The more
unconsolidated and fine-grained the sediment, the flatter the slope
and the farther outside of the channel material will be removed.
In the Miami River, the extent of the slope may also be
influenced by rock and hard material that under lays the channel in
many locations.
Figure
1
Miami River Maintenance
Dredging
Federal
Channel Dredging Project
The
Miami River is a federally authorized channel constructed in the
1930s. The width of the
channel varies from 150 feet wide at the mouth of the river, to 125
feet wide above the NW 17th Avenue bridge, to 90 feet wide
above the NW 27th Avenue bridge.
The federally authorized channel depth is –15 feet mean low
water (MLW). The river
has not been maintained since its construction.
The dredging will restore the original constructed channel
depths and increase efficiency and safety of port operations.
The Miami River dredging project will remove accumulated
infill; no blasting or removal of rock is included.
Funding
is in place for the federal channel dredging which is scheduled to
begin in summer or fall of 2002.
The USACE is responsible for approximately 80% of the project
costs and Miami-Dade County, as the Local Project Sponsor, is
responsible for the remaining 20%.
A local funding partnership including Miami-Dade County, the
City of Miami, the State of Florida, and the Florida Inland Navigation
District has been formed to pay the local dredging share.
Bank
to Bank Option
The
County is considering extending the federal dredging project beyond
the limits of the federal channel, essentially bank to bank.
This would allow contaminated material outside the federal
channel to be removed from the Miami River system.
Figure 2 shows the additional dredging for the bank-to-bank
option.
Figure
2
The
cost of this additional dredging would be the responsibility of the
local funding partnership and it will have to be separately permitted
from the federal project. The
federal government will not participate in the cost but it will
include it in the scheduled contract.
The County is securing permits and pursuing funding options for
this bank-to-bank option.
USACE Set-Back Policy
USACE
policy is to maintain a minimum 25-foot distance between any structure
and the dredging, unless the local sponsor requests a reduction in
this distance. Maintaining
this 25-foot setback would result in significantly reducing width of
the channel in some locations, as well as reducing the volume of
contaminated sediment to be removed from the channel.
Miami-Dade County has requested that the USACE dredge to within
10 feet of structures along the Miami River, as the local sponsor.
Dredging in the Vicinity of
Waterfront Structures
If the
waterfront structure is in poor or substandard condition, the shifting
sediments associated with the dredging could negatively impact the
stability of the structure. Waterfront
structures impacted by dredging fall into three general categories,
based upon location, as shown in Figure 3 and discussed below.
- Waterfront
Structure 1:
If the waterfront structure
is more than 10 feet from the federal navigation channel limits
then the federal dredging project will be to the edge of the
channel. The
bank-to-bank option will extend the dredging to 10 feet of the
structure.
- Waterfront
Structure 2: If
the waterfront structure is less than 10 feet from the federal
navigation channel limits then the federal dredging project and
the bank-to-bank option will also extend to within 10 feet from
the structure.
- Waterfront
Structure 3:
If the waterfront structure
encroaches into the federal channel, federal regulations require
that impediments to navigation be removed from the channel.
The dredging limits after the structure is modified to
eliminate the encroachment will be the same as Structure 1 or 2
above depending upon the modified structure.
Figure
3
If
you have any questions or would like additional information, call
Nancy Case O’Bourke at 305/572-9960 or e-mail at nancy@caseobourke.com.