RIVER COMMISSION GREENWAY SUBCOMMITTEE AND QUALITY OF LIFE JOINT MINUTES: Minutes of meeting |
Mar. 10, 2003 9:00 AM (THIS IS A PUBLIC DOCUMENT) |
|
The
Miami River Commission’s (MRC) Greenway Subcommittee met Monday,
March, 10 2003, at 9 am, in the Miami River Inn, 118 South River Drive.
The attendance sheet is attached.
|
|||
Lavinia Freeman,
Trust for Public Land (TPL), stated TPL contracted Kimley-Horn and
Associates (KHA) to conduct Greenway drainage analysis along the
proposed Greenway route, along both shores, between I-95 and the 5th
Street Bridge. The drainage
analysis currently being conducted by KHA, would be followed by
construction documents for the Greenway in the same area.
TPL is currently reviewing the draft KHA contract for the
construction documents, and the City of Miami’s required “Assignment
Agreement” will be part of the contract, which is expected to be
executed by March 14, 2003. Freeman
stated the estimated price to develop the Greenway along both shores
between I-95 and the 5th ST bridge is $5 million, and the
City of Miami and TPL’s available identified funding is only $100,000
short of that estimated total. Freeman
estimates groundbreaking for this section of the Greenway by Fall 2003. The Greenways subcommittee decided the following two items will be included in their next agenda:
The Greenway
subcommittee decided to switch their regularly scheduled meeting date to
the first Tuesday of every month, 10 am at the City of Miami Riverside
Center, 444 SW 2nd Ave, 3rd Floor Conference Room.
The next Greenway subcommittee meeting will therefore be Tuesday,
April 1, 10 am, Miami Riverside Center, 444 SW 2nd Ave, 3rd
Floor conference room. |
|||