I. Planning Studies/Presentations

A. Presentation of Flagler and 1st Street Reconstruction Options - Mr. Jeff Easley, Florida Department of Transportation (FDOT) project development section, noted FDOT was currently conducting its alternative evaluation process of the PD&E (i.e. obtaining input from the community) in relation to the Flagler and 1st Street reconstruction options. After such input has been collected, Mr. Easley noted FDOT would host a public meeting in May 2007. Mr. Easley introduced Mr. Rene de Huebles, FDOT, and provided the following information regarding the engineering/environmental analysis of the project, which will examine different build alternatives and consist of location, design and concept approval.  Mr. Easley presented an aerial of the subject area and typical cross sections for the two alternatives which remain under construction.  Both of the two evaluated alternatives which remain under consideration maintain on-street parking, and one-way directions, while the “2A” alternative includes bike lanes and the “5B: alternative excludes bike lanes.

Mr. Murley asked if two-waying Flagler and 1st ST were being evaluated, consistent with smart growth and new urbanism principles.  Mr. Easley replied that 2-waying would cause a lot of impacts. Mr. Easley explained that business owners in the area are concerned that expanding the right-of-way would eliminate on street parking in front of their businesses.  Dr. Martin asked if there was an analysis that FDOT could refer to regarding the recent 2-waying of Flagler Street in Downtown Miami, and Mr. Easley replied that since the street was recently converted, more time was needed to study the subject area and its impacts.  Mr. Easley stated construction is expected to commence between 2011-2012, since funding for the entire project is currently unavailable.  Mr. Murley asked if the project would address both bridges (Flagler and 1st Street ), and Mr. Easley replied that bridge analysis is outside the project’s scope of services. 

Mr. Brett Bibeau, MRC Managing Director, reviewed the following:

  • The Flagler Bridge pedestrian staircase is fenced off, also blocking access to a City of Miami Department of Off-Street Parking lot beneath I-95; Mr. Easley and Mr. Huebles replied they had suggested FDOT include recommending the removal of the fence in the PD&E.

  • The City of Miami has construction engineering documents to build an on-road Greenway on City owned public right-of-way beneath the 1st and Flagler Bridges along N. River Drive , co-funded with an FDOT grant.  The FDOT owned riverfront public rights-of-way should be incorporated into the project via removing chain link fences and beautifying the area with landscaping and painting, as recommended in the Miami River Corridor Urban Infill Plan and the Miami River Greenway Action Plan. Mr. Easley and Mr. Huebles replied they had suggested FDOT include this recommendation in the PD&E, and stated FDOT is willing to work with the City of Miami to connect these adjacent riverfront public right of way areas in the upcoming construction of this section of the Miami River Greenway.   Mr. Huebles added FDOT has hired to contractor to clean beneath the Flagler and 1st ST Bridges.

  • Tall trucks heading east on South River Drive are striking the undercarriage of the 1st Street Bridge, forcing them to travel in reverse three blocks to the first possible turn off of S. River Drive onto NW 3 ST.  Therefore, Mr. Bibeau recommended incorporating additional blinking yellow caution lights and more advanced signage warning truckers of clearance, so they may take a right on NW 3 ST to avoid the low clearance.

  • Replace the broken pedestrian light beneath 1st Street Bridge on South River Drive; FDOT agreed

  • Incorporate solid waste interceptors in the reconstructed storm water system of Flagler and First, in order to keep debris from entering the River; FDOT agreed

Mr. Easley noted a public hearing will be held on March 7, 4 pm at the Latin Chamber of Commerce. Mr. Jim Murley, Chair of the UIWG, stated the UIWG recommends the MRC support the alternative with Bike lanes and on street-parking, “2A”.  Ms. Chase noted she would place the item on the March 5, 2007 agenda, and would forward the contact information of all MRC board members to FDOT at least one week prior to the meeting, so that they may submit copies of the project’s crosswalks/necessary materials in preparation for the presentation.

B.  Presentation of Historic East Coast Fisheries - Mr. Bibeau reported he had been informed that Mr. Peter Schwartz, developer of the proposed Miami Riverhouse Lofts, had retracted his original plans for the site which the MRC had found to be consistent with the Miami River Corridor Urban Infill Plan.  The new proposal for the area may include some dry-stack boat storage, therefore MRC staff invited the property owners to present their new plans to the UIWG, and they were unavailable to attend the meeting.  Dr. Martin explained the historically designated site has remained an eyesore to the community for several years, and feared it could potentially face “demolition by neglect”. 

Mr. Weinreb, City of Miami , stated he would be serving as a liaison between the City and the MRC’s Urban Infill Working Group.  Mr. Weinreb noted he had met with DERM to discuss dry slips vs. wet slips, because although dry slips have less impact than wet slips, the Manatee Protection plan regulations are the same for west and dry slips. Mr. Murley noted the city of Aventura was currently experiencing much success with dry stack storage. Mr. Bibeau explained the Manatee Protection Plan would affect the future of dry/wet slips, adding that the Board of County Commissioners is expected to create a committee which would review and update the current manatee protection plan.  Mr. Weinreb offered to look into the status of the East Coast Fisheries site with relation to Code Enforcement violations, and provide any information to the UIWG.  Mr. Bibeau thanked Mr. Robert Weinreb for his time and assistance.   

C. Presentation by Team Metro Melrose- Mr. Bibeau noted Team Metro Melrose had requested to make a presentation before the UIWG regarding illegal dumping, but wasn’t able to attend the meeting.  The UIWG agreed to place the item on any future agenda requested by Team Metro Melrose.

 D. Status of the “MIC Associated Development” Planning Process Mr. Bibeau distributed the revised draft “Upper River Area Plan” summary to the UIWG.  The UIWG asked Mr. Bibeau to extend the boundary on the map depicting the study area to include Palmer Lake , and accepted the document with that revision.  The UIWG directed staff to e-mail the revised final summary to Mr. Sabrata Basu, Assistant Director of the Miami-Dade County Planning and Zoning Department.

E. Status of the Miami River Corridor Multi-Modal Transportation Plan Mr. Bibeau noted he had conducted field work with the Plan’s consultants on January 12, 2007 .  Mr. Bibeau stated he had completed 75% of his preliminary comments on the first complete draft. Mr. Bibeau provided the attendees with the Plan’s draft executive summary, and his comments on the draft.  The UIWG will be provided the full 2nd draft in early March, which will be reviewed during the UIWG’s mid-March meeting, and possibly full the full MRC on April 2, 2007 . Mr. Bibeau noted the item will be presented before the MRC board in April. Mr. Murley recommended that the plan include a timeline, concept map / rendering, and outline the need and purpose of the Plan earlier in the executive summary.  Dr. Martin suggested each transportation improvement recommendation identify the responsible transportation agency to bring the each individual recommendation to fruition.

F. Review and Discuss Updated Draft of Miami 21 East Quadrant –Ms. Chase noted she had spoken to Ms. Luciana Gonzalez, City of Miami Planning Department, whom had informed her that the Miami 21 consultants had yet to schedule any meetings in the near future. Mr. Murley suggested that MRC staff continue to monitor the Miami 21 public planning process, and advocate for the UIWG’s recommended creation of a “Riverside District” to address the specific issues related to riverfront properties, such as increasing the waterfront’s “rear” building setback, requiring publicly accessible riverwalks on new mixed-use and residential developments, creating a waterfront industrial district, etc. Mr. Weinreb stated the City of Miami ’s legal department is reviewing the UIWG’s “Riverside District” idea, and confirmed that no public meetings have been scheduled. Ms. Chase stated Ms. Gonzalez has forwarded the UIWG’s suggestion to create a “Riverfront District” to the consultants, which she noted may be incorporated into the Miami 21 draft.

II. New BusinessThe UIWG reviewed and discussed the following items:

  • Mr. Murley suggested that the MRC partner with the Dade Heritage Trust to compile an ongoing list of historic sites to be included in a future brochure. Mr Bibeau noted the MRC’s Greenways Subcommittee had compiled a list of areas that are appropriate for historic marker installation, which may incorporated into the piece.

  • Mr. Bibeau noted per Mr. Murley’s e-mailed request, he is scheduling a site visit with the Latitude on the River developer, to discuss how their riverwalk which is nearing completion will connect to the east with the Neo Vertika riverwalk and to the west with the 2nd Ave Bridge riverwalk.

The UIWG confirmed its next meeting for March 14, 2007, 10 am, New Board Room, 1407 NW 7 ST.