RIVER COMMISSION URBAN INFILL PLANNING GROUP MINUTES: Minutes of meeting |
July 11, 2001 10:00 AM (THIS IS A PUBLIC DOCUMENT) |
|
The Miami River Commission Urban Infill Subcommittee met Wednesday, July 11, 2001, 9 am, Miami Riverside Center, 444 SW 2nd Ave., 3rd floor conference room. Mr. Jim Murley chaired the meeting. The attendance sheet is enclosed. |
|
||
The Urban Infill
Subcommittee approved the draft Miami River Corridor Planning schedule,
subject to a few revisions including moving the final workshop one month
earlier. The revised
schedule will be e-mailed to the Urban Infill Subcommittee members. The executed
Kimley-Horn contract requires a list of documents to be provided to the
consultants in the current “data collection” phase of the Miami
River Corridor Planning process. Steve Lefton, Kimely-Horn stated this is a “critical
path” in keeping the plan on schedule.
The City, County and Miami River Commission reviewed the executed
Kimley-Horn scope of services’ list of twelve documents to be provided
during “data collection” and assigned the responsible agency to
provide the enumerated documents. The
field survey portion of the “data collection” phase can not commence
until the documents listed in the executed scope of services have been
provided to Kimley-Horn. Kimley-Horn would like to begin field surveys on Monday, July
23, so the Miami River Commission, City and County must provide Kimley-Horn
with all documents prior to July 20. The Urban Infill Working Group decided to meet on the second Wednesday of every month, 9 am, Miami Riverside Center, 3rd floor conference room, therefore the next meeting will be August 8. |
|||