CONTACT
US! MIAMI RIVER COMMISSION Email: |
MIAMI RIVER COMMISSION STORMWATER SUBCOMMITTEE MINUTES: Minutes of meeting |
May 4, 2005 10:00 AM (THIS IS A PUBLIC DOCUMENT) |
|
The Miami River Commission’s (MRC) Stormwater Subcommittee (SSC) met
as regularly scheduled on the first Wednesday of the month, |
|||
I) Miami
River Basin Water Quality Improvement Report Agency Implementation
Progress Report – Mr.
Jose Lago, City of Miami Capital Improvement Department, distributed
copies of the City of Miami’s Miami River Basin Water Quality v
Status of retrofit drainage in remaining areas of v
Status of Allapattah Storm Sewer Project: The
construction for this project was completed in December 2004. The
project is located along v Status of Downtown Storm Sewers Rebuilding Project: This project is divided in two phases: Phase I (SW 15th Road) and Phase II (North Bay Shore Drive at NE 18th Street, NE 17 Terrace, NE 18 Terrace, NE 4 Avenue, NE 19 Street, NE 17 Street). Phase I was completed in August 2002. Phase II consists of drainage improvements and roadway reconstruction. The engineering design consultant assigned to this project is R.J Behar. The design phase is approximately 30% complete. The design commenced in February 2005 and is anticipated for completion in August 2005. Subsequent to procurement phase, construction is expected to begin in February 2006 and be completed in December 2006. The estimated total project cost is not known at this time. Current funding allocated for this project is $671,000 Mr. Steve Blair,
Miami-Dade County Department of Environmental Resource Management (DERM),
asked Mr. Lago for the scope of Phase II of the project. Mr. Lago
responded that he currently did not have those details since the project
is only at 30% design completion, but agreed to verify and provide the
scope before the next regularly scheduled MRC Stormwater Subcommittee
meeting. Mr. Omar Abdelrahman, DERM, asked Mr. Lago about the projects
specific design, and Mr. Lago stated that design notes and details would
be in place by the time the project is at 50% completion. Mr. Lago added
that once the $671,000 in allocated funding is utilized, the City of v Status of Wagner Creek Dredging Project, Phase III, IV and V: According to Mr. Lago, Phase III of the project (between 20th Street and NW 14th Avenue); Phase IV (between 14th Avenue and NW 15 Street); and Phase V (between 15th Street and NW 11 Street), will remain on hold until a temporary storage/dewatering site is identified and a public meeting is held with regards to this site and project. Once the City selects a dredging methodology and a temporary storage/dewatering site is identified and approved, a Corrective Action Plan will be revised and resubmitted to DERM for their review. The City will then conduct publicly noticed meetings to inform residents of plans for the overall project, establish construction costs/estimates, and determine the project’s funding feasibility. Mr. Blair asked for the project’s timeline, and Mr. Lago responded that the City did not have a set time frame since it was currently researching potential staging sites and continuing to evaluate a series of innovative technologies for dredging and dewatering creek sediment. Mr. Brett Bibeau, MRC Managing Director, referred to the April 6, 2005 MRC Stormwater Subcommittee meeting minutes, in which Mr. Lago had stated that the City of Miami expected to select a new temporary staging site by June 2005. Mr. Bibeau asked Mr. Lago if the City would need to extend that timeline and Mr. Lago replied the June site selection may need to be extended indefinitely. Mr. Evan Skornick, South Florida Water Management District (SFWMD), recommended that the City utilize the SFWMD $1 million grant appropriated several years ago for the Wagner Creek dredging project Phases IV and V for engineering and study fees. Mr. Lago thanked him for the suggestion and agreed to pass that information along to his supervisor. Mr. Bibeau asked Mr. Lago if the City would consider conducting a Request for Proposals (RFP) for the Wagner Creek dredging project before it selected a new temporary staging site, as was the case with Miami River Maintenance dredging project. Mr. Lago responded that the City intended to select the site, host a public hearing, refine the cost estimate, secure the necessary funding, followed by selecting the project’s contractor. The entire selection process, noted Lago, would be closely regulated by DERM. Mr. Dieter Bauer, representing Power U, asked Mr. Lago if the City had already selected a company to remove dioxins from Wagner Creek, and Mr. Lago responded that the City was currently examining different options. Mr. Bibeau, on
behalf of MRC board member Dr. Ernie Martin, asked if Phase IV of the
Wagner Creek dredging project would extend further south to include the Mr. Lago noted
he had also discussed with his director the possibility of having the
City of Mr. Bauer
expressed an urgent need to install more advisory signs along Wagner
Creek as soon as possible. Mr. Blair addressed Mr. Bauer’s concerns
and informed meeting attendees that all Wagner Creek neighbors had
received letters nearly two years ago advising them not to fish or swim
along Wagner Creek. Mr. Bauer noted Power U representatives had recently
spoken to the Department of Health, and are considering posting the
signs themselves. Mr. Lago asked Mr. Bauer to please wait for the City
to install the appropriate advisory signs, and Mr. Bauer noted the City
had agreed to posting the advisory signage in 2003. Ms. Elyrosa Estevez,
stated the City’s Print Shop may manufacture the signage, and Public
Works may provide installation.
The SSC recommended if the City of v
Status of Installing Sold Waste Interceptors at all Mr.
Blair then asked if the City had any plans in place to maintain and
clean the soon- to- be- installed solid waste interceptors. Ms. Estevez
responded the City pays $196,640 per year for all outfalls and catch
basins to be inspected and cleaned once a year. Mr. Michael Gambino,
DERM, commented that once a year is insufficient to remove the debris
which will be collected by the new solid waste interceptors. Ms. Estevez
stated that Ms. Barbara Pruitt, City of sweeping of the City’s interceptors, which are also required by the City’s National Pollutant Discharge Elimination System (NPDES) State permit. Ms. Estevez
stated the top two-four feet of contaminated soil adjacent to Wagner
Creek on NW 14 ST are being removed and replaced with clean soil, in
preparation for the “ II.
Status of the Draft Wagner Creek Corrective Action Plan and Dredging
Permit Applications-
As Mr. Lago explained during
his presentation of the City of III.
Update on the Development of TMDL’s for Wagner Creek-
Mr. Blair stated he had met with FDEP and the City of IV. Status of
WASD Smoke Testing of the V.
New Business-
Ms. Estevez stated that the City of Mr. Bibeau
stated he was recently hosting an important Mr. Skornick
stated that the SFWMD had recently completed its “Elephant Gun”
dredging approach in the upper C-4 canal. Skornick stated that the SFWMD
also plans to dredge the S-25 B structure to C-6 ( The next
regularly scheduled SSC meting was confirmed for the first Wednesday of
the month, The meeting
adjourned. |
|||
HOME
CALENDAR
ABOUT THE RIVER
ABOUT
THE COMMISSION DREDGING
GREENWAYS |